98 MAAC CHAMPIONSHIPS
10 COMMISSIONER'S CUPS
Share |

Embed Code

close

Photo Gallery: Leonidoff Field Renovation Photo Gallery... 4/10/2007
Leonidoff Field Renovation Photos
backforward
Embed This
Next Gallery: Marist Softball vs. Fairfield
  • 480 640 April 11, 2007 - The style of stone selected for the grandsatnd's facade is selected. This entire facility will be clad in this style of stone. 206056538 Marist Athletics
    480 640 April 11, 207 - A rear entryway is framed out. The opening at the top will become a louver system that will aid in fresh air intake. 206056539 Marist Athletics
    480 640 April 11, 2007 - More plumbing and now HVAC work continues in the grandstand's bowels serving locker room, rest-rooms, and an athletic training room. 206056540 Marist Athletics
    480 640 April 11, 2007 - Work on the ceiling in front of the concesions area continues. The plywood will eventually be outfitted with epay wood, used throughout the new Leonidoff. 206056541 Marist Athletics
    480 640 April 11, 2007 - A worker carfully smoothes out a completed section of joint compound. This is placed between the sections of precast stadia plank for water tightness. 206056621 Marist Athletics
    480 640 April 11, 2007 - A close-up of a partially completed seam caulking. A small straw-like device is inlaid to allow for air to move within the caulk, or to let it "breathe". 206056623 Marist Athletics
  • 480 640 April 11, 2007 - A completed line of seams between stadia plank are caulked. The seams are covered as the chemicals cure to form a water-tight seal. 206056625 Marist Athletics
    480 640 April 11, 2007 - A samll portion of the berm is shaped. Eventually the berm will border the sideline opposite the grandstand and the two endzones. 206056542 Marist Athletics
    480 640 April 11, 2007 - A wide perspective of the progress at the Leonidoff Field Renovation Project 206056626 Marist Athletics
    480 640 April 18, 2007 - A sample of the cement board is secured to the cast-in-place portion of the grandstand. The interior portins of the grandstand will be clad in this material. 206056426 Marist Athletics
    480 640 April 18, 2007 - Another piece of cement board is used in a mock-up. This shade will be utilized along the bottom of the pressbox windows running end to end along the grandstand. 206056627 Marist Athletics
    480 640 April 18, 2007 - One of the entryways into the press box and luxery suite areas is framed out 206056427 Marist Athletics
  • 480 640 April 18, 2007 - The pressbox's north wall has begun to be assembled. The exterior of this poertion of the box will likewise be clad in a cement board finish. 206056628 Marist Athletics
    480 640 April 18, 2007 - A wide perspective of the progress and activity within the press box and luxery suite areas 206056543 Marist Athletics
    480 640 April 19, 2007 - A new south construction vehicle entrance is established at the Leonidoff Field Renovation job site 206056629 Marist Athletics
    480 640 April 19, 2007 - Brackets are attached along the front of the pressbox precast components. The pressbox framing materials will soon be installed along these brackets. 206056544 Marist Athletics
    480 640 April 23, 2007 - A mock-up of the pressbox window is installed. Different colors of cement board, whic will run the length of the presbox, are located under the window for selection by the project managers. 206056428 Marist Athletics
    480 640 April 23, 2007 - The front of the pressbox begins to be framed with the installation of metal studs. Windows will run along the top of the studs end-to-end. 206056630 Marist Athletics
  • 480 640 April 26, 2007 - One of the pressbox's media booths is frmaed out. Two of these booths will flank the game operations portion of the pressbox. 206056545 Marist Athletics
    480 640 April 26, 2007 - Another perspective of one of the media booths from the ground level of Leonidoff Field, soon to be covered with a FieldTurf playing surface 206056546 Marist Athletics
    480 640 May 3, 2007 - A wide perspective of the shaping of the berm that will border the west side of the facility. This soon-to-be grass covered space will allow for additional spectator seating. 206056547 Marist Athletics
    480 640 May 3, 2007 - Another perspective of the site work at the renovation project. The shaping of the field's north end berm can also be observed in this photo behind the earth moving equipment. 206056548 Marist Athletics
    480 640 May 7, 2007 - An earth mover dumps soil that will become part of the northern berm at the Leonidoff Field project 206056550 Marist Athletics
    480 640 May 10, 2007 - The shaping of the western berm continues. This berm will border the FieldTurf playing surface opposite the grandstand. 206056551 Marist Athletics
  • 480 640 May 10, 2007- A rock vein is discovered on the field surface. The rock must be broekn apart in order for the surface to be properly prepared for the FieldTurf. 206056552 Marist Athletics
    480 640 May 10, 2007 - A wide perspective of the Leonidoff Field site work. The soil in the foreground has been leveled and prepared for the FieldTurf installation. 206056553 Marist Athletics
    480 640 May 10, 2007 - A string line is placed at the field marking the eastern boundary of the FieldTurf DuraSpine playing surface. 206056554 Marist Athletics
    480 640 May 10, 2007 - The FieldTurf playing surface boundary is marked 206056631 Marist Athletics
    480 640 May 10, 2007 - Inside a team room, the plumbing lines are covered in preparation for the spraying of the fire-proofing material to the precast components. 206056429 Marist Athletics
    480 640 May 10, 2007 - The project requires the re-location of a light tower. Here a drill prepares the soil for placement of the new light tower footing. 206056430 Marist Athletics
  • 480 640 May 10 - The base for the soon-to-be re-located light tower is set in it's new location 206056632 Marist Athletics
    480 640 May 10, 2007 - A bulldozer, outfitted with a laser leveling device on it's front blade, prepares and levels the surface for the FieldTurf installation and it's drainage system 206056633 Marist Athletics
    480 640 May 10, 2007 - A trench is dug for the pouring of a concrete curb. This curb will seperate the FieldTurf surface from it's surrondings. 206056555 Marist Athletics
    480 640 May 11, 2007 - The curb that will serve as the FieldTurf border has been poured along the front of the grandstand 206056634 Marist Athletics
    480 640 May 11, 2007 - A corner of the curb border cures at the Leonidoff Renovation site 206056556 Marist Athletics
    480 640 May 11, 2007 - The drain tile, that will be embedded under the FieldTurf surface, awaits installation. 206056557 Marist Athletics
  • 480 640 May 11, 2007 - A concrete curb is poured to form the border between the FieldTurf playing surface and the surronding areas 206056558 Marist Athletics
    480 640 May 11, 2007 - A corner of the curb FieldTurf border has been poured and cures 206056559 Marist Athletics
    480 640 May 11, 2007 - The 12" peremeter drain tile, which will be installed under the FieldTurf, arrives on the project site. 206056560 Marist Athletics
    480 640 May 15, 2007 - The first shipment of Marist stone arrives at the site. This style of stone will be used to clad the exterior of the grandstand. 206056562 Marist Athletics
    480 640 May 15, 2007 - A football upright sleeve has been set in place at one end of the site. This work occurs now before the FieldTurf sub-surface work continues 206056563 Marist Athletics
    480 640 May 15, 2007 - A trench is dug for the FieldTurf's peremeter drain system to be installed 206056564 Marist Athletics
  • 480 640 May 15, 2007 - Black fabric is placed in the trench. This will prevent the surronding earth from coming in contact with the drain tile and restricting flow. 206056638 Marist Athletics
    480 640 May 15, 2007 - A bed of gravel is placed in the trench upon which the drain tile will rest 206056431 Marist Athletics
    480 640 May 15, 2007 - The trench is covered with fabric and a bed of gravel is poured. Now the peremeter drainage system can begin installation. 206056566 Marist Athletics
    480 640 May 17, 2007 - With a slight shift in the field's location, all the fixtures on the light towers must be re-focused to thier new positions. 206056567 Marist Athletics
    480 640 May 17, 2007 - The first pour of sidewalks occurs in front of the grandstand. Approxmately 37,000 square feet of concrete sidewalks will be poured at this project. 206056432 Marist Athletics
    480 640 May 17, 2007 - Black fabric is rolled out over the entire playing surface's fotprint. Two differeing sizes of gravel will then be poured atop this fabric. 206056568 Marist Athletics
  • 480 640 May 18, 2007 - A wide perspective of the progress of the site preparation work for the FieldTurf installation. The fabric barrier is laid along with drainage system work. 206056569 Marist Athletics
    480 640 May 18, 2007 - The thin, laterial drainage componets are installed on the field's surface. These drainage mechanisms carry water to the main drainage system located at the field's peremeter. 206056651 Marist Athletics
    480 640 May 18, 2007 - The first delivery of ipe wood arrives at the site. This material will be used throughout the project site in both exterior and interior applications. 206056653 Marist Athletics
    480 640 May 18, 2007 - Wood is applied to the interior of the peremeter curbing. The FieldTurf will be tied into this material during installation. 206056656 Marist Athletics
    480 640 May 18, 2007 - Work continues on the peremeter drainage system. Gravel is used to cover the drain lines to allow water to penetrate and be carried away. 206056570 Marist Athletics
    480 640 May 20, 2007 - Additional work on the FieldTurf drainage system continues 206056659 Marist Athletics
  • 480 640 May 20, 2007 - The FieldTurf sub-surface work continues. The gravel is smoothed and compacted in preparation for the next layer of fine gravel. 206056571 Marist Athletics
    480 640 May 20, 2007 - A section of the lateral drainage system is seen here. Note how it will run into the main system for superior water removal capabilities. 206056672 Marist Athletics
    480 640 May 21, 2007 - The gravel sub-surface is compacted. The next step will be the fine gravel base and then the FieldTurf playing surface. 206056661 Marist Athletics
    480 640 May 21, 2007 - The next gravel bed is poured for the FieldTurf's sub-surface. This fine gravel will be the surface the FieldTurf backing will be installed upon. 206056673 Marist Athletics
    480 640 May 21, 2007 - A close-up of the difference in gravel types. The fine gravel will be the final top layer upon which the FieldTurf will be laid. 206056674 Marist Athletics
    480 640 May 21, 2007 - The final top layer of fine gravel is spread over the larger sized stone gravel sub-base. This top layer will be smoothed and then compacted. 206056676 Marist Athletics
  • 480 640 May 21, 2007 - A worker begins the process of compacting the final layer of gravel. It must have a very smooth finish and slight crown before the FieldTurf is rolled out. 206056677 Marist Athletics
    480 640 May 21, 2007 - Another concrete of sidewalks in front of the grandstand is completed and smothed. The edge of the FieldTurf playing surface will end at the edge of this sidewalk. 206056678 Marist Athletics
    480 640 May 29, 2007 - The Leonidoff Field sub-surface is prepared and ready to begin the FieldTurf installation. 206056662 Marist Athletics
    480 640 May 29, 2007 - 22 of the 26 rolls of FieldTurf DuraSpine arrive on campus. 206056663 Marist Athletics
    480 640 May 29, 2007 - Concrete forms are delivered to the west side berm. These will be used to form walls where stone will be applied throughout the grassy seating area opposite the grandstand. 206056664 Marist Athletics
    480 640 May 29, 2007 - Stonework begins on the north end of the grandstand. The entire structure will be clad in this stone, along with portions of the spectator berm on the opposite site of the field. 206056665 Marist Athletics
  • 480 640 May 29, 2007 - A protective covering is applied to the main expension joint along portions of the precast stadia plank 206056679 Marist Athletics
    480 640 May 31, 2007 - The remaining four rolls of FieldTurf are delivered along with the rubber and silica sand infill system 206056680 Marist Athletics
    480 640 May 31, 2007 - The fireproofing is sparyed onto the precast components inside one of the locker rooms. This will then be covered with a gray colored paper-based product final layer. 206056666 Marist Athletics
1/69