98 MAAC CHAMPIONSHIPS
10 COMMISSIONER'S CUPS
Share |

Embed Code

close

Photo Gallery: Leonidoff Renovation Project 2/5/2007
backforward
Embed This
Next Gallery: Marist Softball vs. Fairfield
  • 480 640 February 6, 2007 - Additional forms are built for the footings of the interior walls. The footings contain some of the rough electric and plumbing. This area shown will be near the equipment manager's office and laundry room 206056320 Marist Athletics
    480 640 February 6, 2007 - Additional interior wall footing forms are built. In the photo's background previously poured interior wall footings have cured and are ready for the construction of the walls of the concessions and rest-room areas. 206056494 Marist Athletics
    480 640 February 12, 2007 - A worker smoothes a section of freshly poured concrete floor. This area will become the future concessions stand. 206056321 Marist Athletics
    480 640 February 12, 2007 - Another section of the area under the seating is prepared for a concrete pour as the rebar has been laid 206056322 Marist Athletics
    480 640 February 13, 2007 - Another section of the floor slab has been poured and is smoothed. This area will become part of the loundry and equipment rooms. 206056323 Marist Athletics
    480 640 February 13, 2007 - A wider persepctive of the activity under the grandstand's seating. This space is heated allowing work to continue through the winter months. 206056324 Marist Athletics
  • 480 640 February 13, 2007 - Additional interior wall footing forms are built that will contain the rough electric work seen here in the foreground 206056325 Marist Athletics
    480 640 February 16, 2007 - Another section of flooring cures under the grandstand. This area will eventually become one of the locker rooms and the laundry room. 206056326 Marist Athletics
    480 640 February 21, 2007 - Yet another concrete pour is mechanically smoothed. With this most recent pour the flooring is now approximately 75% complete. 206056393 Marist Athletics
    480 640 February 21, 2007 - The most recent pour is soothed and left to cure. This area will contain another 55 locker locker room and a portion of the training room. 206056327 Marist Athletics
    480 640 February 21, 2007 - Work continues on the most recent concrete pour. An unseasonably warm winter day in Poughkeepsie provides optimal conditions. 206056328 Marist Athletics
    480 640 Fenruary 26, 2007 - With most of the floor slab poured, the assembly of the interior metal wall studs has begun 206056329 Marist Athletics
  • 480 640 February 26, 2007 - A wide perspective of the installation of the wall studs under the grandstand 206056394 Marist Athletics
    480 640 February 26, 2007 - A void in the block-work that forms the elevator shaft. This will become the entryway into the elevator car. 206056330 Marist Athletics
    480 640 February 28, 2007 - Workers on a lift install the top rail of the wall studs. This future wall will seperate the women's rest-room from the concessions area. 206056331 Marist Athletics
    480 640 February 28, 2007 - More interior walls have begun construction 206056332 Marist Athletics
    480 640 February 28, 2007 - Concrete forms are built surrounding the main electrical service areaa. The forms will become bridges, or footings to carry the load on the interior walls. 206056495 Marist Athletics
    480 640 March 1, 2007 - Another interior wall section has been built. Now electrical and plumbing work will continue around the frame. 206056333 Marist Athletics
  • 480 640 March 5, 2007 - A wide perespective of the work continuing under the Leonidoff Field grandstand 206056334 Marist Athletics
    480 640 March 5, 2007 - The steel pressbox components have begun assmebly atop the precast grandstand structure 206056335 Marist Athletics
    480 640 March 5, 2007 - Another perspective of the pressbox steel components 206056336 Marist Athletics
    480 640 March 5, 2007 - The pressbox steel awaits the remainder of the components to complete the assembly 206056337 Marist Athletics
    480 640 March 5, 2007 - The assemebly of the walls studs continues under the grandstand. Areas such as the training room, laundry room and locker rooms and being framed out. 206056338 Marist Athletics
    480 640 March 8, 2007 - Plumbers install overhead pipe hangars for the fire supression system 206056339 Marist Athletics
  • 480 640 March 8, 2007 - Rough plumbing work has begun. This work will serve a portion of the women's rest-room. 206056497 Marist Athletics
    480 640 March 8, 2007 - Additional steel components have been installed. The pressbox & suites will occupy this space framed out in the steel. 206056341 Marist Athletics
    480 640 March 14, 2007 - Activity continues in the bowels of the grandstand. 206056498 Marist Athletics
    480 640 March 21, 2007 - The frame of the drop ceiling is assembled under the grandstand. It will cover the training room, laundry room and eqipment room 206056499 Marist Athletics
    480 640 March 21, 2007 - The rest-rooms continue to be framed and outfitted with the rough plumbing and electrical work 206056397 Marist Athletics
    480 640 March 21, 2007 - A wide perspective of progress under the grandstand at the Leonidoff Field renovation project 206056343 Marist Athletics
  • 480 640 March 29, 2007 - The steel frame work on the Leonidoff Field pressbox is complete. The roof decking is also underway as seen in the photo. 206056398 Marist Athletics
    480 640 March 29, 2007 - A void in the steel will allow for the placement of the venue's speakers. The opening of the elevator shaft can be noted in the background. 206056500 Marist Athletics
    480 640 March 29, 2007 - Metal studs are in place to form the covered area in front of the rest-rooms and concessions. This covering will be outfitted with epay wood. 206056344 Marist Athletics
    480 640 March 29, 2007 - Work continues under the grandstand. The area covered in the photo's foreground will become the athletic training room. 206056346 Marist Athletics
    480 640 March 29, 2007 - A light fixture is installed in a void in the cast-in-place concrete wall. This light will illuminate one of the six aisle staircases leading to field level. 206056399 Marist Athletics
1/35