Photo Gallery: Leonidoff Field Renovation Photo Gallery... 12/5/2006
Leonidoff construction photos
backforward
Embed This
Next Gallery: Marist Softball vs. Fairfield
  • 480 640 December 1, 2006 - Structural fill is delievered to the site. This fill is then compacted in preparation for the pour of the flooring of the locker rooms & other areas. 206056257 Marist Athletics
    480 640 December 1, 2006 - Structural fill is continued to be spread along the foundation. It will be compated to the height of the concrete forms in the photo's forground. 206056258 Marist Athletics
    480 640 December 5, 2006 - The structural fill has been backfilled up to the columns. Soon the columns will receive the racker beams. 206056288 Marist Athletics
    480 640 December 5, 2006 - A wide shot of the progress of the Leonidoff Renovation project. All grandstand colums are in place and ready the receive the racker beams. 206056289 Marist Athletics
    480 640 December 6, 2006 - A racker beam is lifted in preparation for it's placement 206056259 Marist Athletics
    480 640 December 6, 2006 - A racker beam is carefully moved into position straddling two columns. 206056260 Marist Athletics
  • 480 640 December 6, 2006 - A racker beam is lowered into it's final placement over two threaded rods allowing for very little margin of error 206056290 Marist Athletics
    480 640 December 6, 2006 - A close up of one of the racker beams-note it's placement over the threaded rods showing how precise the alignment must be 206056261 Marist Athletics
    480 640 December 6, 2006 - The first three racker beams are set that span the "A" and "B" Column rows. Next they will receive the stadia plank. 206056262 Marist Athletics
    480 640 December 6, 2006 - The racker beams spaning columns lines "A" and "B" are complete. 206056291 Marist Athletics
    480 640 December 6, 2006 - The first of the stadia plank pre-cast components is off-loaded for placement 206056292 Marist Athletics
    480 640 December 6, 2006 - Stadia plank is set atop the racker beams. The stadia plank will eventually be outfitted with spectator seating 206056263 Marist Athletics
  • 480 640 December 7, 2006 - Gravel is spread and compacted over the future footprint of usable space under the grandstand 206056264 Marist Athletics
    480 640 December 7, 2006 - Workers carefully guide a section of stadia plank into position straddling two raker beams 206056265 Marist Athletics
    480 640 December 7, 2006 - A wide perspective of the lower sections of stadia plank. Soon more raker beams and stadia plank will extend to the back line of columns. 206056293 Marist Athletics
    480 640 December 7, 2006 - Placement of the final section of stadia plank on the lower portion of the grandstand 206056294 Marist Athletics
    480 640 December 7, 2006 - The lower portion of the stadia plank is complete. Next the craine must be moved to the rear of the facility for additional assembly. 206056295 Marist Athletics
    480 640 December 7, 2006 - A wide shot of the current progress of the Leonidoff Field Renovation Project 206056266 Marist Athletics
  • 480 640 December 8, 2006 - Workers lower and set the first section of stadia plank over column lines "B" and "C'" or the rear of the facility 206056267 Marist Athletics
    480 640 December 8, 2006 - The first section of stadia plank is placed and work will continue along the top portion of the grandstand 206056296 Marist Athletics
    480 640 December 11, 2006 - The grandstand continues to grow as additional stadia plank components are set in place 206056378 Marist Athletics
    480 640 December 11, 2006 - A view of the rear of the grandstand. The structure will eventually be enclosed and outfitted with team and training rooms underneath. 206056268 Marist Athletics
    480 640 December 7, 2006 - The top line of raker beams and stadia plank continue to be erected. 206056297 Marist Athletics
    480 640 December 11, 2006 - A section of stadia plank is lifted. Each piece weighs in at approxmately 8,000 pounds. 206056269 Marist Athletics
  • 480 640 December 11, 2006 - The section of stadia plank is carfully giuded into place by the erectors. 206056270 Marist Athletics
    480 640 December 11, 2006 - A wide shot of the current progress of the Leonidoff Renovation Project as the grandstand precast work continues 206056298 Marist Athletics
    480 640 December 11, 2006 - Excavation work has begun on the south end of the site. This will contain the sand filter that all waster water from the grandstand will pass through. 206056271 Marist Athletics
    480 640 December 13, 2006 - Work continues on the waste water sand filter as rebar and concrete forms are assembled. Soon the concrete walls will be poured. 206056380 Marist Athletics
    480 640 December 13, 2006 - The grandstand staia plank now encloses the facility's footprint. The base of the elevator shaft is shown in the foreground wrapped in a moisture barrier. 206056472 Marist Athletics
    480 640 December 13, 2006 - The last two remaining voids between raker beams requiring stadia plank installation. Next precast components will applied to the rear of the facility. 206056381 Marist Athletics
  • 480 640 December 13, 2006 - One of the final placements of stadia plank precast 206056473 Marist Athletics
    480 640 December 13, 2006 - The team of precast erectors skillfully guides one of the final stadia plank components into place along the top of the grandstand 206056382 Marist Athletics
    480 640 December 13, 2006 - After the stadia plank is set, seams exisit between the pieces. Each seam will be filled and double-caulked to ensure a water tight seal. 206056474 Marist Athletics
    480 640 December 13, 2006 - After the plank is set, stainless steel pins are set near the seams to ensure no plank shiffting occurs during temperature changes 206056383 Marist Athletics
    480 640 December 14, 2006 - Workers insert pins into each of the back-row columns in preparation for the placements of the rear wall components 206056475 Marist Athletics
    480 640 December 14, 2006 - The large rear wall pieces, each weighing approximately 30,000 pounds, are moved into position straddling the grandstand's columns 206056384 Marist Athletics
  • 480 640 December 14, 2006 - The white lines along each piece are styrofoam which are set during the casting process. They will be later removed in order to apply the stone facade. 206056299 Marist Athletics
    480 640 December 14, 2006 - Work continues along the rear of the grandstand with the placement of the upper wall precast components 206056385 Marist Athletics
    480 640 December 14, 2006 - The precast pieces that will become the base of the pressbox are set. The will become areas for game operations, working media and hospitality. 206056300 Marist Athletics
    480 640 December 14, 2006 - A steel weld plate is cast into componets of the base of the pressbox. The steel work that will become the pressbox structure will be welded to this plate. 206056386 Marist Athletics
    480 640 December 14, 2006 - The New York State EPA required waster water sand filer's concrete walls have been poured. All waste and storm sewer lines will be tied into this filter. 206056301 Marist Athletics
    480 640 December 28, 2006 - The removal of the old Leonidoff Field seating grandstand is underway 206056302 Marist Athletics
  • 480 640 December 28, 2006 - Removal of the old grandstand seats continues. This area will become a grassy berm that will allow for additional spectator seating. 206056303 Marist Athletics
    480 640 December 28, 2006 - The aisle steps are added to the precast stadia planks 206056477 Marist Athletics
    480 640 December 28, 2006 - Work has completed on the grandstand's waste water sand filter 206056478 Marist Athletics
    480 640 December 28, 2006 - A campus road is repaved after having the storm sewer lines tied into the existing system 206056304 Marist Athletics
    480 640 January 2, 2007 - The removal of the old grandstand seating structure continues. Only the old press box is left standing which will likewise soon be removed. 206056479 Marist Athletics
    480 640 January 4, 2007 - Concrete cures on a very mild winter day in Poughkeepsie. This will become the foundation for one of the six grandstand entryway staircases. 206056305 Marist Athletics
  • 480 640 January 4, 2007 - The block work begins on the south end of the grandstand wrapping around the base of the elevator shaft shown in this photo's right-hand side. 206056480 Marist Athletics
    480 640 January 4, 2007 - The scaffolding along the grandstand's north end is assembeled and covered in drop cloths to keep the heat in and the winter weather out 206056481 Marist Athletics
    480 640 January 4, 2007 - Portable gas-powered heaters are in place at the site. They will heat the area under the grandstand to allow work to continue on the interior rooms. 206056306 Marist Athletics
    480 640 January 4, 2007 - A wide shot of the current progress of the Leonidoff Field renovation project 206056482 Marist Athletics
    480 640 January 4, 2007 - Another wide perespective of the renovation project taken from atop the old pressbox slated for demolition the following day 206056307 Marist Athletics
    480 640 January 11, 2007 - Scaffolding is erectyed along the grandstand's south end allowing for block work to begin. The block will eventually be clad in the Marist field stone. 206056483 Marist Athletics
  • 480 640 January 11, 2007 - An electrician pulls string lines through a portion of the grandstand's foundation where conduit enters the space. 206056484 Marist Athletics
    480 640 January 11, 2007 - Block work is near completetion on the grandstand's north end. Stone hangers are embeded into the mortar lines for ease of stone application to the wall. 206056387 Marist Athletics
    480 640 January 11, 2007 - Masons apply three differing types of stone to the front of the grandstand. This area will help the project managers decide what particular of stone to use throughout. 206056308 Marist Athletics
    480 640 January 17, 2007 - A trench is dug for the installation of the waste water line under the grandstand. It will serve areas such as the locker rooms, training room and concessions stand and rest-rooms 206056485 Marist Athletics
    480 640 january 17, 2007 - Temporary weather barriers are installed to help keep the space heated. This will allow work to continue during the winter months. 206056309 Marist Athletics
    480 640 January 17, 2007 - The north end block work is complete. A green mesh-like fiber is aqpplied to the wall. This will allow for water and rain to weep away from behind the stonework that will eventually cover this wall. 206056486 Marist Athletics
  • 480 640 January 17, 2007 - One of the six stairways for spectator entry into the grandstand are prepared for the next concrete pour. The stairway's facade will eventually be outfitted with the Marist field stone. 206056388 Marist Athletics
    480 640 January 22, 2007 - The rough plumbing work continues within the area under he grandstand. The floor slab will be poured once the rough plumbing and electrci work are complete. 206056310 Marist Athletics
    480 640 January 25, 2007 - The rough plumbing work continues. This work will become the waste water floor drains in the locker rooms, rest-rooms and other spaces under the grandstand seating. 206056311 Marist Athletics
    480 640 January 25, 2007 - More rough plumbing work. This area will serrve the concessions area of the facility. 206056312 Marist Athletics
    480 640 January 25, 2007 - Rough electric work progresses at the Leonidoff Field Renovation Project 206056313 Marist Athletics
    480 640 January 25, 2007 - A wide-shot of the rough plumbing and electric work. Once work is complete, the concrete floor can be poured and the interior work will continue. 206056389 Marist Athletics
  • 480 640 January 30, 2007 - Forms are built that will serve as the footings for the interior walls of the space under the grandstand. This area pictured will become the concessions area & rest-rooms. 206056390 Marist Athletics