October 2, 2006 - Concrete forms are delivered to the site
206055893Marist Athletics
480640
October 2, 2006 - Concrete forms are delivered to the site
206055895Marist Athletics
480640
October 2, 2006 - Existing landscaping is cleared from the construction site
206055866Marist Athletics
480640
October 2, 2006 - The temporary fence is erected separating the playing field from the construction zone
206055896Marist Athletics
480640
October 3, 2006 - The footprint of the future grandstand is excavated. Concrete footings will then be poured upon which them precast stadium columns will be placed.
206055897Marist Athletics
480640
October 3, 2006 - More excavation work continues at the Leonidoff Field renovation project site.
206055898Marist Athletics
480640
October 4, 2006 - The excavated soil is collected. It will then be transported to the opposite side of the facility to act as the fill material for a 12 foot high grass covered berm for additional spectator seating.
206055899Marist Athletics
480640
October 4, 2006 - Excavation work continues along the length of the future footprint of the grandstand. A depth of six feet must be achieved before the foundation work begins.
206055900Marist Athletics
480640
October 5, 2006 - More gravel is in place in the foundation pit of the future grandstand
206055618Marist Athletics
480640
October 5, 2006 - Gravel is pourded in the foundation pit upon which the grandstand columns will be placed
206055871Marist Athletics
480640
October 5, 2006 - More excavation work continues at the Leonidoff Field renovation project
206055901Marist Athletics
480640
October 5, 2006 - A wide-shot of the current progress of the construction of the new Leonidoff Field grandstand
206055972Marist Athletics
480640
October 6, 2006 - Excavation work continues at the site in preparation for the foundation and grandstand column footings
206055902Marist Athletics
480640
October 6, 2006 - Gravel waiting to be pourded into the foundation pit
206055903Marist Athletics
480640
October 6, 2006 - A wide-shot of construction activity
206055974Marist Athletics
480640
October 6, 2006 - A worker ensures that the proper depth of the foundation pit is achieved
206055619Marist Athletics
480640
October 9, 2006 - The foundation pit's excavation work nears completion
206055620Marist Athletics
480640
October 9, 2006 - Final detail excavation work is performed with a small backhoe
206055978Marist Athletics
480640
October 9, 2006 - The remaining ground water from the foundation pit is pumped out
206055621Marist Athletics
480640
October 9, 2006 - The excavated soil continues to be collected which will become the fill material for the grassy berm
206055979Marist Athletics
480640
October 10, 2006 - Concrete forms are lowered into the foundation pit for assembly
206055981Marist Athletics
480640
October 10, 2006 - The concrete forms, placed throughout the foundation pit, await assembly
206055622Marist Athletics
480640
October 10, 2006 - Concrete forms are assembled. 24 forms wil be built and the grandstand foundation columns will be placed upon each form.
206055982Marist Athletics
480640
October 10, 2006 - More concrete forms are placed in the foundation pit
206055984Marist Athletics
480640
October 11, 2006 - Storm drain lines are installed and buried at the project site
206055985Marist Athletics
480640
October 11, 2006 - Concrete forms continue to be assembled within the foundation pit
206055987Marist Athletics
480640
October 11, 2006 - More concrete forms are assembeled in preperation for the grandstand columns
206055909Marist Athletics
480640
October 11, 2006 - A rock vein is discovered under the future grandstand's footprint. The rock is broken apart and removed from the foundation.
206055989Marist Athletics
480640
October 24, 2006 - A worker lays rebar into the concrete form in preparation for the foundation pour
206055990Marist Athletics
480640
October 24, 2006 - The installation of the storm drain continues at the Leonidoff Field renovation project
206055992Marist Athletics
480640
October 25, 2006 - Work continues on assembling the rebar web inside one of the concrete forms
206055993Marist Athletics
480640
October 25, 2006 - The rebar assembly is complete within one of the concrete forms. It now awaits the concrete pour and then the precast grandstand column.
206055918Marist Athletics
480640
October 26, 2006 - Rebar work nears completion within the grandstand foundation pit
206055994Marist Athletics
480640
October 26, 2006 - More grandstand foundation completed rebar work stands ready for the foundation pour
206055924Marist Athletics
480640
October 30, 2006 - The concrete pump extends it's arm in preparation for the foundation pour
206055925Marist Athletics
480640
October 30, 2006 - Concrete is emptied into the concrete pump for delivery into the foundation forms
206055997Marist Athletics
480640
October 30, 2006 - A project milestone is achieved-the first foundation pour of the future Leonidoff Field Grandstand
206055926Marist Athletics
480640
October 30, 2006 - The foundation is continued to be poured into one of the forms where a grandstand column will be placed
206055927Marist Athletics
480640
October 30, 2006 - A worker uses a vibrator to ensure no air bubles exist within the concrete once it is poured
206056001Marist Athletics
480640
October 30, 2006 - A wide-shot of the foundation pour and the current state of the construction progress
206056003Marist Athletics
480640
October 31, 2006 - Concrete cures within the grandstand foundation forms
206056004Marist Athletics
480640
October 31, 2006 - Workers trowel and smooth the concrete within one of the foundation's box footings
206055928Marist Athletics
480640
October 31, 2006 - A wide perspective of the grandstand's foundation as the concrete cures
206055929Marist Athletics
480640
October 31, 2006 - A fully poured foundation box footing cures. Approxminately 20 yards, or two fully loaded concrete trucks, is required to fill one of these footings.
206056006Marist Athletics
480640
November 1, 2006 - The first two rows of grandstand foundation footings are ready to begin receiving wall forms and columns
206055931Marist Athletics
480640
November 1, 2006 - A foundation component with the exposed rebar in the center of the footing. The rebar must match up with voids on the bottom of each grandstand column during assembly.
206055932Marist Athletics
480640
November 1, 2006 - The future grandstand's front and center foundation footings with exposed rebar
206056010Marist Athletics
480640
November 1, 2006 - Excavation work begins to clear the area for the grandstand's rear foundation and wall
206055934Marist Athletics
480640
November 2, 2006 - Wall forms are laid out for assembly. They will be used to form the grandstand's west wall.
206055935Marist Athletics
480640
November 2, 2006 - The assembly of the grandstand's wall forms begins
206056014Marist Athletics
480640
November 2, 2006 - The west wall forms continue to be assembled along the foundation's footing
206055936Marist Athletics
480640
November
206056016Marist Athletics
480640
November 2, 2006 - The rebar that will be embeded within the wall form's concrete pour is assembled
206055938Marist Athletics
480640
NOvember 3, 2006 - The wall forms for the grandstand's west wall continued to be assembled.
206055939Marist Athletics
480640
November 3, 2006 - More grandstand wall forms rise out of the foundation pit as work continues
206055940Marist Athletics
480640
November 6, 2006 - Gravel is poured in the nearly completed back portion of the foundation pit. The now exposed field lighting electric lines are seen in this photo.
206055636Marist Athletics
480640
November 6, 2006 - A wide perspective of the foundation pit and the assembly of the concrete forms that will become the grandstand's west wall
206055941Marist Athletics
480640
November 6, 2006 - Work continues on the assembely of the concrete forms that will soon become the grandstand's west wall
206055942Marist Athletics
480640
November 7, 2006 - The back row of grandstand column footings are framed upon a bed of gravel in preparation for the concrete pour
206056020Marist Athletics
480640
November 7, 2006 - A close-up of one of the back row of footings. Note the electrical conduit running across the footing. It contains the field's lighting electric lines which would normally be buried in the field.
206056021Marist Athletics
480640
November 7, 2006 - The rock vein, running partially under the grandstand's footprint, is further removed to make way for the foundation
206056023Marist Athletics
480640
November 7, 2006 - The current state of the construction progress at the Leonidoff Field renovation project
206055944Marist Athletics
480640
November 15, 2006 - Another project marker-the first concerete pour of the grandstand's walls. The wall being poured here will become the front wall of the structure.
206055637Marist Athletics
480640
November 15, 2006 - The concrete pump continues to work as the grandstand's west wall is poured
206055945Marist Athletics
480640
November 15, 2006 - The two western walls are poured. The shorter wall will become the interior back wall of spaces such as the locker rooms and training room.
206055638Marist Athletics
480640
November 16, 2006 - As the concrete has cured, the forms are removed to reveal the grandstand's west wall.
206055946Marist Athletics
480640
November 16, 2006 - The freshly poured concrete cures on the grandstand's back row of column footings
206055947Marist Athletics
480640
November 16, 2006 - More concrete forms are removed at the Leonidoff Field renovation project site
206056025Marist Athletics
480640
November 27, 2006 - The arrival of the pre-cast components at the project site
206055639Marist Athletics
480640
November 27, 2006 - The pre-cast components are lifted off the trailer and then lowered and set into place
206055948Marist Athletics
480640
November 27, 2006 - Another project milestone is achieved-the first pre-cast component is set into place as part of the grandstand's structure
206056027Marist Athletics
480640
November 27, 2006 - Additional pre-cast components of the "A" row of columns are set upon a bed of concrete and mortar
206056028Marist Athletics
480640
November 27, 2006 - A wide-shot of the first day of pre-cast component placement at the Leonidoff Field renovation project
206056029Marist Athletics
480640
November 27, 2006 - A back row or "C" row column is placed. On top of the column a racker beam will be placed upon which the stadia decking will be installed.
206056030Marist Athletics
480640
November 27, 2006 - The back row column is in place with the middle row, or "B" row, column pictured in the foreground
206056031Marist Athletics
480640
November 27, 2006 - The plywood is removed from the front of the grandstand. The Marist field stone will then be applied as the facility's facade.
206055949Marist Athletics
480640
November 28, 2006 - The back row, or "c" row of pre-cast grandstand columns continue to grow out of the foundation pit
206056032Marist Athletics
480640
November 28, 2006 - The remainder of the "C" row grandstand columns are placed. Next the raker beams and finally the stadium plank will be set in place.
206056033Marist Athletics
480640
November 28, 2006 - Work continues as the concrete forms are installed in preparation for the foundation's back wall concrete pour
206055950Marist Athletics
480640
November 28, 2006 - Activity in the foundation pit as placement of the pre-cast grandstand columns nears completion
206055951Marist Athletics
480640
November 30, 2006 - With the "A" row of columns set, structural fill is compacted in the grandstand's crawlspace
206055952Marist Athletics