98 MAAC CHAMPIONSHIPS
11 COMMISSIONER'S CUPS
Share |

Embed Code

close

Photo Gallery: Leonidoff Renovation Project 10/3/2006
backforward
Embed This
Next Gallery: Marist Softball, 2013 MAAC...
  • 480 640 October 2, 2006 - Concrete forms are delivered to the site 206055893 Marist Athletics
    480 640 October 2, 2006 - Concrete forms are delivered to the site 206055895 Marist Athletics
    480 640 October 2, 2006 - Existing landscaping is cleared from the construction site 206055866 Marist Athletics
    480 640 October 2, 2006 - The temporary fence is erected separating the playing field from the construction zone 206055896 Marist Athletics
    480 640 October 3, 2006 - The footprint of the future grandstand is excavated. Concrete footings will then be poured upon which them precast stadium columns will be placed. 206055897 Marist Athletics
    480 640 October 3, 2006 - More excavation work continues at the Leonidoff Field renovation project site. 206055898 Marist Athletics
  • 480 640 October 4, 2006 - The excavated soil is collected. It will then be transported to the opposite side of the facility to act as the fill material for a 12 foot high grass covered berm for additional spectator seating. 206055899 Marist Athletics
    480 640 October 4, 2006 - Excavation work continues along the length of the future footprint of the grandstand. A depth of six feet must be achieved before the foundation work begins. 206055900 Marist Athletics
    480 640 October 5, 2006 - More gravel is in place in the foundation pit of the future grandstand 206055618 Marist Athletics
    480 640 October 5, 2006 - Gravel is pourded in the foundation pit upon which the grandstand columns will be placed 206055871 Marist Athletics
    480 640 October 5, 2006 - More excavation work continues at the Leonidoff Field renovation project 206055901 Marist Athletics
    480 640 October 5, 2006 - A wide-shot of the current progress of the construction of the new Leonidoff Field grandstand 206055972 Marist Athletics
  • 480 640 October 6, 2006 - Excavation work continues at the site in preparation for the foundation and grandstand column footings 206055902 Marist Athletics
    480 640 October 6, 2006 - Gravel waiting to be pourded into the foundation pit 206055903 Marist Athletics
    480 640 October 6, 2006 - A wide-shot of construction activity 206055974 Marist Athletics
    480 640 October 6, 2006 - A worker ensures that the proper depth of the foundation pit is achieved 206055619 Marist Athletics
    480 640 October 9, 2006 - The foundation pit's excavation work nears completion 206055620 Marist Athletics
    480 640 October 9, 2006 - Final detail excavation work is performed with a small backhoe 206055978 Marist Athletics
  • 480 640 October 9, 2006 - The remaining ground water from the foundation pit is pumped out 206055621 Marist Athletics
    480 640 October 9, 2006 - The excavated soil continues to be collected which will become the fill material for the grassy berm 206055979 Marist Athletics
    480 640 October 10, 2006 - Concrete forms are lowered into the foundation pit for assembly 206055981 Marist Athletics
    480 640 October 10, 2006 - The concrete forms, placed throughout the foundation pit, await assembly 206055622 Marist Athletics
    480 640 October 10, 2006 - Concrete forms are assembled. 24 forms wil be built and the grandstand foundation columns will be placed upon each form. 206055982 Marist Athletics
    480 640 October 10, 2006 - More concrete forms are placed in the foundation pit 206055984 Marist Athletics
  • 480 640 October 11, 2006 - Storm drain lines are installed and buried at the project site 206055985 Marist Athletics
    480 640 October 11, 2006 - Concrete forms continue to be assembled within the foundation pit 206055987 Marist Athletics
    480 640 October 11, 2006 - More concrete forms are assembeled in preperation for the grandstand columns 206055909 Marist Athletics
    480 640 October 11, 2006 - A rock vein is discovered under the future grandstand's footprint. The rock is broken apart and removed from the foundation. 206055989 Marist Athletics
    480 640 October 24, 2006 - A worker lays rebar into the concrete form in preparation for the foundation pour 206055990 Marist Athletics
    480 640 October 24, 2006 - The installation of the storm drain continues at the Leonidoff Field renovation project 206055992 Marist Athletics
  • 480 640 October 25, 2006 - Work continues on assembling the rebar web inside one of the concrete forms 206055993 Marist Athletics
    480 640 October 25, 2006 - The rebar assembly is complete within one of the concrete forms. It now awaits the concrete pour and then the precast grandstand column. 206055918 Marist Athletics
    480 640 October 26, 2006 - Rebar work nears completion within the grandstand foundation pit 206055994 Marist Athletics
    480 640 October 26, 2006 - More grandstand foundation completed rebar work stands ready for the foundation pour 206055924 Marist Athletics
    480 640 October 30, 2006 - The concrete pump extends it's arm in preparation for the foundation pour 206055925 Marist Athletics
    480 640 October 30, 2006 - Concrete is emptied into the concrete pump for delivery into the foundation forms 206055997 Marist Athletics
  • 480 640 October 30, 2006 - A project milestone is achieved-the first foundation pour of the future Leonidoff Field Grandstand 206055926 Marist Athletics
    480 640 October 30, 2006 - The foundation is continued to be poured into one of the forms where a grandstand column will be placed 206055927 Marist Athletics
    480 640 October 30, 2006 - A worker uses a vibrator to ensure no air bubles exist within the concrete once it is poured 206056001 Marist Athletics
    480 640 October 30, 2006 - A wide-shot of the foundation pour and the current state of the construction progress 206056003 Marist Athletics
    480 640 October 31, 2006 - Concrete cures within the grandstand foundation forms 206056004 Marist Athletics
    480 640 October 31, 2006 - Workers trowel and smooth the concrete within one of the foundation's box footings 206055928 Marist Athletics
  • 480 640 October 31, 2006 - A wide perspective of the grandstand's foundation as the concrete cures 206055929 Marist Athletics
    480 640 October 31, 2006 - A fully poured foundation box footing cures. Approxminately 20 yards, or two fully loaded concrete trucks, is required to fill one of these footings. 206056006 Marist Athletics
    480 640 November 1, 2006 - The first two rows of grandstand foundation footings are ready to begin receiving wall forms and columns 206055931 Marist Athletics
    480 640 November 1, 2006 - A foundation component with the exposed rebar in the center of the footing. The rebar must match up with voids on the bottom of each grandstand column during assembly. 206055932 Marist Athletics
    480 640 November 1, 2006 - The future grandstand's front and center foundation footings with exposed rebar 206056010 Marist Athletics
    480 640 November 1, 2006 - Excavation work begins to clear the area for the grandstand's rear foundation and wall 206055934 Marist Athletics
  • 480 640 November 2, 2006 - Wall forms are laid out for assembly. They will be used to form the grandstand's west wall. 206055935 Marist Athletics
    480 640 November 2, 2006 - The assembly of the grandstand's wall forms begins 206056014 Marist Athletics
    480 640 November 2, 2006 - The west wall forms continue to be assembled along the foundation's footing 206055936 Marist Athletics
    480 640 November 206056016 Marist Athletics
    480 640 November 2, 2006 - The rebar that will be embeded within the wall form's concrete pour is assembled 206055938 Marist Athletics
    480 640 NOvember 3, 2006 - The wall forms for the grandstand's west wall continued to be assembled. 206055939 Marist Athletics
  • 480 640 November 3, 2006 - More grandstand wall forms rise out of the foundation pit as work continues 206055940 Marist Athletics
    480 640 November 6, 2006 - Gravel is poured in the nearly completed back portion of the foundation pit. The now exposed field lighting electric lines are seen in this photo. 206055636 Marist Athletics
    480 640 November 6, 2006 - A wide perspective of the foundation pit and the assembly of the concrete forms that will become the grandstand's west wall 206055941 Marist Athletics
    480 640 November 6, 2006 - Work continues on the assembely of the concrete forms that will soon become the grandstand's west wall 206055942 Marist Athletics
    480 640 November 7, 2006 - The back row of grandstand column footings are framed upon a bed of gravel in preparation for the concrete pour 206056020 Marist Athletics
    480 640 November 7, 2006 - A close-up of one of the back row of footings. Note the electrical conduit running across the footing. It contains the field's lighting electric lines which would normally be buried in the field. 206056021 Marist Athletics
  • 480 640 November 7, 2006 - The rock vein, running partially under the grandstand's footprint, is further removed to make way for the foundation 206056023 Marist Athletics
    480 640 November 7, 2006 - The current state of the construction progress at the Leonidoff Field renovation project 206055944 Marist Athletics
    480 640 November 15, 2006 - Another project marker-the first concerete pour of the grandstand's walls. The wall being poured here will become the front wall of the structure. 206055637 Marist Athletics
    480 640 November 15, 2006 - The concrete pump continues to work as the grandstand's west wall is poured 206055945 Marist Athletics
    480 640 November 15, 2006 - The two western walls are poured. The shorter wall will become the interior back wall of spaces such as the locker rooms and training room. 206055638 Marist Athletics
    480 640 November 16, 2006 - As the concrete has cured, the forms are removed to reveal the grandstand's west wall. 206055946 Marist Athletics
  • 480 640 November 16, 2006 - The freshly poured concrete cures on the grandstand's back row of column footings 206055947 Marist Athletics
    480 640 November 16, 2006 - More concrete forms are removed at the Leonidoff Field renovation project site 206056025 Marist Athletics
    480 640 November 27, 2006 - The arrival of the pre-cast components at the project site 206055639 Marist Athletics
    480 640 November 27, 2006 - The pre-cast components are lifted off the trailer and then lowered and set into place 206055948 Marist Athletics
    480 640 November 27, 2006 - Another project milestone is achieved-the first pre-cast component is set into place as part of the grandstand's structure 206056027 Marist Athletics
    480 640 November 27, 2006 - Additional pre-cast components of the "A" row of columns are set upon a bed of concrete and mortar 206056028 Marist Athletics
  • 480 640 November 27, 2006 - A wide-shot of the first day of pre-cast component placement at the Leonidoff Field renovation project 206056029 Marist Athletics
    480 640 November 27, 2006 - A back row or "C" row column is placed. On top of the column a racker beam will be placed upon which the stadia decking will be installed. 206056030 Marist Athletics
    480 640 November 27, 2006 - The back row column is in place with the middle row, or "B" row, column pictured in the foreground 206056031 Marist Athletics
    480 640 November 27, 2006 - The plywood is removed from the front of the grandstand. The Marist field stone will then be applied as the facility's facade. 206055949 Marist Athletics
    480 640 November 28, 2006 - The back row, or "c" row of pre-cast grandstand columns continue to grow out of the foundation pit 206056032 Marist Athletics
    480 640 November 28, 2006 - The remainder of the "C" row grandstand columns are placed. Next the raker beams and finally the stadium plank will be set in place. 206056033 Marist Athletics
  • 480 640 November 28, 2006 - Work continues as the concrete forms are installed in preparation for the foundation's back wall concrete pour 206055950 Marist Athletics
    480 640 November 28, 2006 - Activity in the foundation pit as placement of the pre-cast grandstand columns nears completion 206055951 Marist Athletics
    480 640 November 30, 2006 - With the "A" row of columns set, structural fill is compacted in the grandstand's crawlspace 206055952 Marist Athletics
1/81